As Asher Lane residents prepare themselves for a week’s total road closure, it seems motorists and property owners along Loughborough Road will have to put up with delays and disruption for even longer after ‘delays in the schedule’ resulted in yet another revised end-date being issued for completing major roadworks there.
The highway reconstruction at the Mere Way Roundabout to create a suitable access for the new William Davis Homes development on former Green Belt farmland began in September 2020. It was originally scheduled for completion on March 26th 2021 but will not now be finished until at least Friday 25th June* – three months behind schedule.
Meantime Bloor Homes has revealed a full closure of Wilford Road – adjacent to its construction site – will be required for a whole week in August.**
These are just three of several sets of disruptive highway works taking place in Ruddington at the moment or in the next few months. The full list scheduled (so far) is below:-
- Extended until Sunday 13th June 2021 – 24-hour multi-way traffic signals for road widening works – Asher Lane between Top Rd and Musters Rd junctions – in association with Avant Homes housing development. These will now continue right up to the total road closure.
- Monday 14th June – Friday 18th June 2021 – Road Closure to complete road widening works – Asher Lane between Top Rd and Musters Rd junctions – in association with Avant Homes housing development. Diversion via The Green, High Street, Kirk Lane, Elms Park, Moor Lane, Leys Road, Barleylands and vice versa. Read more >>HERE<<.
- Extended until Sunday 20th June – Footpath closure on High Street for new shop/office development at former Barclay & Cook store (below) – Drivers please beware pedestrians in road. This will be followed by a total road closure***.
- *Extended until Fri 25th June 2021 – Multi-way 24-hour traffic lights – A60 Loughborough Road on the eastern side of the roundabout at the junction with Mere Way – To install a toucan crossing point, widen the footway, upgrade street lighting, install a new access for the William Davis housing development, upgrade existing surface water drain, widen approaches onto the roundabout, resurface the carriageway, add white lining and anti skid surface. {The plan of this work is shown below.}
- **Tuesday 1st June to Sunday 1st August 2021 – 24 hour two-way traffic signals on Wilford Rd approx. 100m north of Paget Close junction – Site entrance construction, road widening, and drainage works the new ‘Fairham Green’ housing development. This will be followed by a FULL ROAD CLOSURE here from Monday August 2nd to Sunday August 8th for completion of this work. {Official, diversionary route to follow.}
- ***Monday 21st June 9.00am to 4.00pm – High Street closure between its junctions with Church Street and Kirk Lane – Western Power Distribution installing new electricity supply – diversion via Easthorpe Street – Loughborough Road – Kirk Lane and vice versa.
- Monday 28th June 2021 08:00 hours until 16:00 hours – closure of Parkyns Street outside numbers 1-17 – Western Power Distribution installing new electricity supply.
Residents and visitors are warned of potential delays for drivers and passengers using Kinchbus 9, CT4N Services 22 & 23, Nottingham City Transport Navy 3, and Green 10C/10X Rushcliffe Country Park/Ruddingtion Fields buses, and the NottsBus Connect Service 863 during the above work.
{NOTE: The above details are subject to potential change due to the weather and other operational reasons. RUDDINGTON.info will provide updates on our website whenever we can.}